Transgrid appointed operator of Hunter Transmission Project

Close-up of a high-voltage transmission tower with blue sky overhead
Image: Shutterstock

The New South Wales Government has appointed Transgrid as Network Operator of the Hunter Transmission Project—critical state significant infrastructure designed to strengthen NSW’s grid.

The new 110km transmission line will deliver a critical connection between the Renewable Energy Zones in Central-West Orana and New England, enabling access to cheaper renewable energy for millions of consumers across the state, as coal generation retires.

Related article: AER rejects Transgrid’s bid to recoup cost blowout

EnergyCo led planning and procurement for the project, with construction contracts also awarded to Downer for transmission lines and UGL for substations, with both companies having extensive experience delivering major energy infrastructure.

Transgrid will now manage delivery of the project before operating and maintaining the new infrastructure over the long term, with EnergyCo continuing its planning and oversight role as Infrastructure Planner.

“EnergyCo has been an important partner in enabling this kind of infrastructure to be developed. Our focus now is on delivering this essential transmission infrastructure safely and efficiently for the NSW Government as the state transitions to a more reliable, secure and affordable energy future,” Transgrid CEO Brett Redman said.

“EnergyCo, Transgrid, and our construction partners understand the importance of working closely and respectfully with communities, landholders, councils and other key stakeholders to deliver major infrastructure projects.

“We are all committed to undertaking the delivery and operation of this critical economic and system security infrastructure in a respectful and responsible way.

“The project will also deliver a wide range of social and economic benefits to the broader Hunter region including construction jobs, supply contracts for local businesses, education and training opportunities, environmental initiatives, and community funding and partnerships.”

Related article: Academia meets actuality at Transgrid

The project team will now focus on detailed design, engineering and management plans before construction begins next year in line with the conditions of approval.