Kidston hydro declared coordinated project

Genex Power’s $330 million Kidston Pumped Hydro Storage project has been declared a coordinated project.

The 250MW project, located at the decommissioned Kidston Gold Mine within Etheridge Shire, proposes an innovative use of two existing adjacent water-filled mine pits to generate hydroelectricity.

Genex CEO James Harding said he welcomed the coordinated project declaration.

“This declaration is recognition of the significant positive benefits that the project will have to the region and state,” Mr Harding said.

“Coming on the heels of the development approval announced last week, it provides further support from the Office of the Coordinator General as we finalise outstanding environmental approvals ahead of closing the financing and commencing construction in 2019.”

Minister for State Development, Manufacturing, Infrastructure and Planning Cameron Dick said the project could employ 370 people during the two-year construction and have a minimum lifespan of 50 years.

“When complete, Stages 1 and 2 of the Kidston Renewable Energy Hub will provide enough energy to power around 160,000 Australian homes – enough power for a city bigger than Cairns,” he said.

“Genex has set a strong mandate to provide local residents with job opportunities, whether that be direct on-site employment, consultancy or indirect contract work.

“This renewable energy project has the ability to revitalise the local economy and I commend Genex on making sure locals benefit from the project.”

Minister for Natural Resources, Mines and Energy Anthony Lynham said the project could act as a large-scale battery storage, allowing solar energy from the adjoining solar project to be stored and harnessed as peak-load power on demand.

“The project complements the Palaszczuk Government’s target of generating 50 per cent of Queensland’s electricity needs from renewable energy by 2030 and is part of state’s $5 billion pipeline of financially committed or underway renewable energy projects,” Dr Lynham said.

“The addition of hydroelectric generation in Far North Queensland will add stability to the network in the region reducing the necessity for importing excess electricity from neighbouring areas, providing a benefit to the entire network.

The Kidston Renewable Energy Hub comprises:

  • Stage 1 solar power project (50MW) which has been constructed
  • Stage 2 proposed new solar project (270MW) to integrate with the K2H project (250MW) currently undergoing assessment
  • Stage 3 wind farm project (150MW) which is in the feasibility stage.

Energy generated by Stage 2 (combined solar and hydro) will be via a new transmission line connecting the Kidston site to Mount Fox, near Ingham.

If approved, construction is due to commence in 2019 and expected to be completed by 2021.