The Gold Fields group’s Agnew gold mine has embraced wind, solar and battery storage to reduce costs and emissions, becoming the first mine in Australia to install wind turbines.
Located nearly 1,000km north-east of Perth, the Gold Fields Group’s Agnew Gold Mine is on track to source approximately 60 per cent of its overall energy needs from renewables.
Related article: Wind farm collab gives power to entrepreneurs
Gold Fields partnered with EDL to design the hybrid off-grid system, approaching ARENA for support to deliver the first of its kind project.
ARENA announced $13.5 million in funding in 2019, building on previous support for renewable energy projects in the mining sector that includes solar deployments at Rio Tinto’s Weipa bauxite mine and Sandfire Resources’ DeGrussa copper and gold mine.
The Agnew project has broken new ground, becoming the first Australian mine to install wind turbines and also claiming the title of Australia’s largest hybrid renewable energy microgrid.
The five new 110m-tall wind turbines have a collective output of 18MW, which is paired with a 4MW solar farm that contains nearly 11,000 panels.
Excess power from the wind turbines and solar farm is stored in a 13MW/4MWh battery, with gas and diesel generators on standby to provide backup power.
So far, the system is meeting expectations and on track to provide between 50 and 60 per cent of the site’s energy needs from renewables, with predictions that wind and solar will provide up to 95 per cent of demand at times.
An advanced energy management system allows for innovative practices that maximise the use of renewable energy, including dynamic load management and shedding and forecasting of future wind and solar production.
The hybrid system was commissioned at the height of the pandemic, officially opening in late 2021.
Announcing the completion of the project, EDL said the microgrid integrates the five technologies to achieve 99.99 per cent reliability, which was a non-negotiable requirement to meet the demands of off-grid mining operations.
EDL CEO James Harman paid credit to the team that delivered the project on time and on budget, despite the challenges caused by the pandemic and bushfires.
“Credit must go to Gold Fields for its vision and belief that we would successfully deliver this complex project; and credit must go also to the entire project team, including EDL and all our contractors, who worked tirelessly to safely deliver the Agnew Hybrid Renewable Project on time and on budget,” Harman said.
Related article: Wind and solar match coal generation output
He pledged to continue to work to allow others to share in the benefits of renewable energy.
“As the energy transition continues at pace, our ultimate goal is 100 per cent renewables, and we look forward to continuing our work to make this a reality.”