Final tower installed in Australia’s biggest transmission build

Large construction crew poses for photo underneath massive transmission tower held up by crane
The last tower rises for Project EnergyConnect (Image: Transgrid)

The last of 1,500 steel towers have been constructed on Australia’s largest electricity transmission project, completing the 700km backbone of EnergyConnect in New South Wales.

Transgrid and construction partner Elecnor Australia have erected the final tower at Bundure in the Riverina region, marking a significant milestone for the nation-critical project which will increase renewable energy sharing between NSW, South Australia and Victoria.

Line stringing works have also been completed, with 10,385km of high-voltage conductor cabling installed, enough to span from Sydney to Perth three times.

Related article: First towers rise in HumeLink transmission project

Transgrid executive general manager of major projects Gordon Taylor said 1,508 towers and monopoles have been erected from the South Australian border to Wagga Wagga and into Victoria, using 46,068 tonnes of structural steel.

EnergyConnect is the first major transmission project to accelerate Australia’s renewable energy transition and will help strengthen the national grid and position NSW as a leader in clean energy,” Taylor said.

“The project is part of our plan to give industry and consumers peace of mind as coal generation winds down in NSW, stabilising the grid at a time when reliability and affordability are national priorities.

“We have achieved extraordinary progress in construction of the project this year, which is now 90% complete and on schedule to be finished in 2026.

“Installation of the final tower and completion of line stringing works caps off a massive logistical operation and construction effort involving up to 1,700 personnel working in parallel across a 700km project alignment.

“As part of our commitment to sustainability, the project includes 733 guyed towers which require 21% less steel and 15% less concrete to construct compared to conventional self-supporting structures. We have also used low carbon concrete in all tower foundations.

EnergyConnect has seen the first Danubio towers erected in Australia, with 338 of the structures specially designed for the 500 kV line between Bundure, near Coleambally, and Wagga Wagga. Each of these towers weighs an average of 60 tonnes and takes 16 days to construct.

Related article: Dinawan substation rises from paddock for EnergyConnect

“Construction of the project has provided an economic boom for regional NSW, including much-needed jobs, skills development, education, training and local business support in communities across the EnergyConnect corridor.”

The 159km western section of EnergyConnect, from Buronga, NSW to the South Australia border and Red Cliffs in Victoria, has already been completed and energised, including construction of one of the biggest and most complex substations in the Southern Hemisphere.

Construction of the world-class Dinawan substation at Bundure is being finalised, and a major expansion of Wagga Wagga substation has also been completed.

Previous articleIn(Tellegen)t grid design avoids the half-Nelson of the NEM
Next articleVestas to install latest wind turbine tech at Palmer Wind Farm