Twenty projects selected in oversubscribed CIS tender

Wind turbines and solar panels (aware super)
Image: iStock

The Australian Government has selected 20 renewable generation and storage projects in its fourth Capacity Investment Scheme (CIS) tender, which attracted projects totalling 25.6GW in renewable capacity—more than four times the 6GW target.

Related article: First long-duration storage tender for South Australia

Twelve projects include large-scale batteries, with a combined storage capacity of 3.5GW/11.4GWh or enough to support the peak load of over 2.6 million households for four hours.

Almost half of the total generation capacity will be delivered by wind projects, including Tasmania’s first CIS project, the Bell Bay Wind Farm, reflecting strong investment in Australia’s wind industry.

Together, the successful projects have committed an estimated $291 million in shared community benefits and $348 million in First Nations benefits such as revenue sharing agreements, First Nations subcontracting, training, and workforce development.

Minister for Climate Change and Energy Chris Bowen said, “The Capacity Investment Scheme continues to be popular and competitive, delivering cheaper, cleaner and more reliable energy for all Australians for years to come.

“We are rebuilding Australia’s energy grid to make it modern, reliable and fair and attracting global interest in our wind and solar.

“The scheme is not only delivering clean power, but also creating thousands of high quality jobs, often in remote and rural areas, and opportunities to train the next generation of engineers, electricians and tradespeople who will build our energy future.”

Related article: Lithium-ion battery projects lead landmark CIS tender

Successful projects in CIS Tender 4 are as follows:

Project

Proponent

Technology

Capacity MW

State

Bell Bay Wind Farm

Equis

Wind

224

Tas

Bendemeer Energy Hub

Athena Energy Australia

Solar + battery
(150 MW/ 300 MWh)

252

NSW

Bundey BESS and Solar

Genaspi Energy Group

Solar + battery
(300 MW/ 1200 MWh)

240

SA

Carmody’s Hill Wind Farm

Aula Energy

Wind

247

SA

Corop Solar Farm and BESS

BNRG Leeson

Solar + battery
(290 MW/ 704 MWh)

230

Vic

Derby Solar Project

Sungrow

Solar + battery
(95 MW/ 210 MWh)

95

Vic

Dinawan Wind Farm (Stage 1)

Spark Renewables

Wind

357

NSW

Gawara Baya

Windlab

Wind + battery
(104 MW/ 217 MWh)

399

Qld

Guthrie’s Gap Solar Power Station

Edify Energy

Solar + battery
(300 MW/ 1200 MWh)

300

Qld

Hexham Wind Farm

AGL

Wind

600

Vic

Liverpool Range Wind Stage 1

Tilt Renewables

Wind

634

NSW

Lower Wonga Solar Farm

Lightsource BP

Solar

281

Qld

Merino Solar Farm

EDPR

Solar + battery
(450 MW/ 1800 MWh)

450

NSW

Middlebrook Solar Farm

TotalEnergies Total Energies Renewables Australia Pty Ltd

Solar + battery
(320 MW/ 813 MWh)

363

NSW

Moah Creek Wind Farm

Central Queensland Power (CQP)

Wind

360

Qld

Nowingi Solar Power Station

Edify Energy

Solar + battery
(300 MW/ 1200 MWh)

300

Vic

Punchs Creek Solar Farm

EDPR

Solar + battery
(400 MW/ 1600 MWh)

400

Qld

Smoky Creek Solar Power Station

Edify Energy

Solar + battery
(300 MW/ 1200 MWh)

300

Qld

Tallawang Solar Hybrid

Potentia Energy

Solar + battery
(500 MW/ 1000 MWh)

500

NSW

Willogoleche 2 Wind Farm

ENGIE and Foresight

Wind

108

SA