Specialist teams go into overdrive to progress EnergyConnect

Crane trucks working on transmission towers in regional Riverina town
Image: Transgrid

Australia’s largest energy transmission project has moved into overdrive with specialist teams making significant progress constructing the eastern alignment of EnergyConnect across the Riverina region.

Related article: EnergyConnect ticks Wagga Wagga substation upgrade

More than 1,600 personnel are working on the nation-critical project with construction of two sections of new high-voltage transmission line, stretching 540km from Buronga to Wagga Wagga, now over 70% complete.

Construction of a world-class substation at Dinawan, near Coleambally, is also proceeding at pace, with major foundations works completed and sophisticated electrical equipment arriving from Europe.

Major upgrades to the Wagga Wagga substation have been completed to prepare the eastern end of the project for connection to the NSW grid.

Transgrid and its construction partner Elecnor Australia are delivering the 700km NSW section of EnergyConnect from Wagga Wagga to the South Australian border with a connection to Victoria.

Transgrid executive general manager of major projects Gordon Taylor said, “EnergyConnect is critical to Australia’s energy transition, connecting households and businesses in the Riverina and across the state with more affordable renewable energy from three states.

“The Riverina is at the heart of the renewable energy transition and the region is currently a hive of construction activity as this nation-building project powers ahead, bringing significant benefits to local communities and energy consumers.”

Progress on the eastern alignment includes:

  • All 1,150 tower foundations have been drilled and poured, using more than 53,000 cubic metres of concrete
  • 1,002 out of 1,150 steel towers have been erected, comprising 330kV freestanding and guyed towers (Buronga to Dinawan) and Australia’s first 500kV Danubio towers (Dinawan to Wagga Wagga)
  • 278km out of 540km of high-voltage conductor cabling has been strung
  • Two synchronous condensers have arrived at the Dinawan substation and will be assembled and housed in a large-scale machine hall. These sophisticated units, which weigh 200 tonnes each, will enhance grid stability as renewable energy sources increase
  • The expansion and upgrade of the Wagga Wagga 330kV substation at Gregadoo have been successfully completed, encompassing civil, mechanical, and electrical works. These included importing 9,500m³ of fill, building 13 new gantries, supported by 83 concrete piles and 272 foundations, and 6,000 hours of testing.

Related article: Nation-critical EnergyConnect West becomes operational

The 159km western section of EnergyConnect, from Buronga to South Australia and into Victoria, was completed and energised earlier this year.

Previous articleGood Earth Green Hydrogen & Ammonia project to go ahead
Next articleQld’s Greenbank Battery begins commercial operation