Jemena has announced construction of the Northern Gas Pipeline (NGP) is complete.
The 622km pipeline links Tennant Creek in the Northern Territory to Mt Isa in Queensland.
Approximately 34,000 lengths of pipe have been welded, lowered and now fully buried in the trench.
“The sheer scale of this project is enormous – the largest current gas pipeline project in Australia,” Jemena executive general manager of corporate development Antoon Boey said.
“This milestone is due to the fantastic effort of those working in remote, hot and often dusty conditions.
“Overall the project is tracking on schedule. Apart from the pipeline, we’re thrilled construction of the Mount Isa Compressor Station is finished and completion of the Phillip Creek Compressor Station in the Northern Territory is imminent.”
The pipeline and both compressor stations will now be rigorously checked before gas commissioning later this year.
“When Jemena was awarded the contract to develop and construct the NGP in 2015 we committed to constructing the pipeline on time, safely, providing training and employment opportunities for people from the communities surrounding the pipeline, and introducing competition into the east-coast gas market,” Mr Boey said.
“What we’re seeing today is these promises being fulfilled. We are so proud of how the NGP has provided training, development, and other opportunities to people from the communities surrounding the pipeline.
“Almost 800 jobs have been created as part of the pipeline’s planning and construction phase – around 700 of which have been awarded to people from local communities along the pipeline route.
“Plus we’ve seen $120 million spent with businesses in the Northern Territory and Queensland.”
Mr Boey said the Northern Territory had a unique opportunity to grow its economy and contribute to the east coast gas shortage.
“Jemena is progressing its plans to extend and expand the Northern Gas Pipeline and will continue to work with the community to understand how they can contribute to this next phase of growth and activity,” he said.
On commissioning, the NGP can deliver 90 TJs of much needed gas per day, with 70 per cent of available capacity in year one having already been contracted to support manufacturing and jobs in Northern Australia.
Last month, Jemena announced its agreement with Incitec Pivot Limited (IPL) to transport at least 32TJs of gas per day to supply its Gibson Island facility.
This follows Jemena’s foundation agreement with the Northern Territory’s Power and Water Corporation to transport 31TJs of gas to IPL’s Phosphate Hill facility for 10 years.