Australian renewables projects have been committed to construction at an all-time record rate during the third quarter of 2026, with large-scale wind and battery projects setting the pace.
Large-scale wind and battery projects made significant headway on the capacity gap for the federal government’s target of 82% renewables by 2030, according to the latest update of the Australian Renewable Energy Scorecard from the Institute for Energy Economics and Financial Analysis (IEEFA) and Green Energy Markets.
Related article: Renewables investment in Australia hits record high
Progress was particularly strong in Queensland, Western Australia, and South Australia.
The Q3 2026 edition of the Scorecard shows a 2.4GW jump in projects financed for construction, 20% above the previous record set in Q1 2022. Wind makes up the lion’s share of new capacity in the last quarter, with 1.5GW committed to construction.
Qld now has more than 90% of the wind turbines under construction that are needed to bridge the gap to its 2030 requirements under the Australian Energy Market Operator (AEMO)’s Integrated System Plan. Meanwhile, WA and SA have closed 60% of the gap to their 2030 wind capacity requirements.
Green Energy Markets CEO and co-author of the scorecard Tristan Edis said, “Qld and WA’s rapid renewable progress is largely due to these state governments stepping in to support power purchase agreements. They did this either directly via their state-owned utilities, or also in Queensland’s case by providing support for Rio Tinto’s Gladstone Smelter to contract renewable energy.
“A substantial share of the credit for Queensland’s progress this quarter is actually down to actions taken by the previous state government. It serves to illustrate that government policies to drive transformation of the electricity system can take time to bear fruit, after which progress can be quite rapid.”
An area where rapid progress is very clearly evident is batteries. In the April-June quarter, the scorecard noted that the utility-scale batteries in construction at that point would provide 21% of the new energy storage capacity needed by 2030 across Australia’s main grids.
Projects committed to construction in the July-September quarter added a further 13%. At this rate, the remaining capacity gap to 2030 could be in construction in less than one and a half years.
Related article: New steel mill to be backed by renewables PPA
Large-scale renewable and battery projects already in construction are providing around $8 billion in investment and 21,600 job years of employment.
If the remaining, fully approved renewable and large-scale battery projects proceed to construction, it would result in around $51 billion in investment and 142,500 job years of employment.