The first 100 battery units have been installed at AGL’s 500MW Tomago Battery in New South Wales’ Hunter Region, marking a major construction milestone for the $800 million project.
The Tomago Battery is one of the new battery storage projects AGL is developing as it transitions its portfolio, with the company planning to add 12GW of renewable and firming capacity by the end of 2035 across a range of projects.
Related article: AGL’s Abermain BESS secures environmental approval
Once operational, the Tomago Battery will be able to store enough electricity to operate at full capacity for up to four hours.
In May 2026, the Tomago Battery was awarded underwriting support by the New South Wales Government through the Long-Term Energy Service Agreement (LTESA) scheme.
Concrete foundations have been laid at the Tomago construction site, and the first 100 of the more than 400 battery units that will make up the large-scale storage project are now in place.
Work on the substation is well advanced, with the first of two main transformers arriving last week. Teams are also continuing to lay electrical cabling and install inverters.
The Tomago Battery’s construction milestone comes two months after AGL’s nearby 500 MW Liddell Battery, beside the former power station, reached practical completion.
AGL general manager construction Johan Myburgh said, “The installation of the first batch of 100 battery units is an important milestone as we work to deliver the 500MW Tomago Battery on schedule in late 2027.
Related article: AGL faces class action over ‘carbon neutral’ claims
“Australia’s energy transition needs a mix of new projects to help power homes and businesses, and AGL’s Tomago Battery will play an important role by storing electricity ready to be discharged later.”