Technology group Wärtsilä has announced that the 150MW/300MWh Bungama BESS it developed for Revera Energy in South Australia has begun commercial operations.
The Bungama battery project strengthens South Australia’s ability to manage record levels of renewable energy while supporting grid reliability across the National Electricity Market (NEM). It is built to respond to fast changes in grid variability, including solar and wind output, with precision. South Australia regularly operates with some of the world’s highest levels of variable renewable generation, making advanced storage infrastructure essential to maintaining energy stability and reliability.
Related article: Construction begins on Bungama BESS in South Australia
The first stage of the Bungama energy storage system processed through the commissioning testing phase ahead of schedule, completing each of the three Hold Point Tests in quick succession. This enabled the project to progress smoothly from commissioning to full commercial operation under Australian Energy Market Operator (AEMO) requirements. Hold Point Tests are AEMO mandated commissioning approvals that allow new energy assets to move in stages from limited operation to full commercial output, confirming safe and reliable performance at each step.
Revera CEO Daniel Kim said, “Bungama BESS is a cornerstone asset in Revera’s strategy to build the flexible infrastructure Australia needs for its clean energy future.
“Working alongside Wärtsilä and our project partners, this project demonstrates what effective collaboration can deliver, while meeting the high technical and safety standards required for the grid.”
Wärtsilä Energy Storage vice president global operations Don Lee said, “Delivering the first stage of the Bungama energy storage system in one of the world’s most dynamic renewable markets demonstrates what advanced technology and deep system collaboration can achieve.
“This project shows how storage can be deployed at pace to support regions operating at the frontier of the energy transition, helping to stabilise the grid and ensure more secure, reliable energy for local communities.”
At the core of the project is Wärtsilä Energy Storage’s GridSolve Quantum High Energy (HE) technology, which features advanced safety architecture and a high energy-density design. The grid-connected site is orchestrated by Wärtsilä’s GEMS platform, which fine-tunes operations in real time and provides rapid frequency response with millisecond-level accuracy.
Related article: Akaysha’s Orana BESS reaches commercial operation
Wärtsilä worked closely with AEMO, transmission network service provider ElectraNet, and Balance of Plant (BOP) contractor Enerven to ensure safe transport, high-quality engineering, and a streamlined commissioning process within one of the world’s most demanding grid environments.